logo search
The_PRINCE2_Process_Model_Book - с пометками

Delivery

Team Manager

Based on OGC PRINCE2® material. Reproduced under license from OGC

Stages - Execution

Close

Fig 3.22 Authorize project closure

PRINCE2 recommends the following actions for the Project Board:

  1. Review the End Project Report, and compare it to the original plan.

  1. Confirm who should receive the Follow on Action Recommendations. e.g.: the persons responsible for the maintenance

  1. Review the Lessons Report and pass it on so it can benefit future projects.

  1. Confirm that products have been handed over, and confirm user acceptance and maintenance for each product.

  1. Review and approve the Benefits Review Plan, as reviewing the benefits will continue to be done after the project shuts down.

  1. Confirm that the project has met the Business Case by comparing the current Business Case to the original one, comparing the Benefits, Cost, Risks, and Return on Investment.