Delivery

Team Manager

-- Once during project

-- Once per stage

-- Many times during stage

-- Once per Work Package

Notification -- Notification

Work Package

Work Package

Work Package Completed WP

MP Outputs Team Plans Checkpoint Reports

Auth.

-- Authorization

Managing Product Delivery (MP)

Quality Register

Com pleted WP

Mgmt Prod -- Management Product

Based on OGC PRINCE2® material. Reproduced under license from OGC

Products get created & quality approved

Pre-Project Initiation Stages - Execution Close

Fig 4.1 The PRINCE2 Process Model diagram

I suggest that you read this book a few times or listen to the podcast version. If you wish to test your knowledge, then try some of the questions in the next section, “Learn Thru Questions”. This is also available as a podcast. You could also try to fill in the exercise sheets.