logo
The_PRINCE2_Process_Model_Book - с пометками

Cs: Project Manager Day to day activities

Before we move to the Managing a Stage Boundary process, let us look at the different activities that are done by the Project Manager in the Controlling a Stage process.

There are eight activities in the Controlling a Stage process. They are divided into three parts that also describe what the Project Manager does:

  1. Deal with Work Packages

  2. Do Monitoring and Reporting

  3. Deal with Issues

    • The Work Package activities are:

      • Authorize a Work Package – meaning assign and agree with the Team Manager so that the Team Manager knows what to do and can create their team plan.

      • Review Work Package Status – check on work package progress, so read Checkpoint reports and check the Quality Register.

      • Receive Completed Work Packages – which is to receive the completed products back from the Team Manager and confirm that they have been quality-checked and stored, as described in the configuration management document.

Corp..

Corporate or Programme Management

www.Mgm tPlaza.com